Emergency Diesel Generators for Storm Shelters and Community Centres

When a hurricane, ice storm or flood is forecast, local authorities open schools, sports halls and community centres as shelters. Hundreds of people may arrive with medication, medical devices and young children, often just as the grid starts to fail. A shelter without power quickly becomes a dark, hot or cold room with no way to cook, charge phones or keep medicines cool.

This guide covers how to plan an emergency diesel generator for a building that will serve as a shelter: the loads that matter, how to size the set, where to put it, how much fuel to store and how to keep it ready in a building that spends most of the year as a school or sports venue.

Start with the shelter role

Agree with the emergency management agency what the building is expected to do. A short-term refuge that people use for a night during a storm needs far less than a shelter expected to house people for a week after a flood. Write down the expected occupancy, the duration, whether people with medical needs will be accepted and whether the building will also act as a distribution point for water and supplies.

Those decisions set every other part of the design. They also clarify who pays: some regions fund generators for designated shelters, and the funding body may set its own rules on sizing, runtime and testing.

List the essential loads

A typical shelter list includes lighting in sleeping, toilet and circulation areas, fire alarm and emergency lighting, heating or cooling for at least the main hall, ventilation, the kitchen and food refrigeration, a medicine fridge, power outlets for medical devices such as oxygen concentrators, phone charging stations, communications equipment and the domestic water booster pumps. Where the building has a sewage lift pump, that belongs on the list too.

Rank the loads so the design can drop the less important ones if needed. Our guide to load priority planning for emergency generators explains how to set up that ranking and connect it to automatic load shedding.

A simple sizing example

Suppose a school sports hall and adjacent kitchen will shelter around 300 people. Lighting for the shelter areas might draw 15 kW, heating or cooling of the main hall 60 kW, the kitchen and refrigeration 40 kW, water pumps and ventilation 20 kW, and outlets for medical devices, charging and communications 25 kW. That gives about 160 kW of running load.

Add allowance for motor starting, especially compressors and pumps, and margin for growth, and the generator might be specified at around 250 kVA. The figures are illustrative; real sizing uses the building’s actual equipment. Our generator sizing chart helps convert between kW, kVA and amps.

Whole building or shelter panel

There are two basic approaches. One connects the generator to the whole building through a main transfer switch, which is simple but needs a large set and may waste fuel on classrooms that are empty during the emergency. The other installs a dedicated shelter panel that carries only the essential circuits, with a smaller generator sized to match.

The shelter panel approach usually gives longer runtime from the same fuel and makes testing easier. It does require the electrician to move the right circuits onto the panel and label them clearly, so that shelter staff know which outlets work during an outage.

Siting above the flood and out of the wind

A generator placed at ground level in a flood zone will fail when it is needed most. Install the set, its fuel tank, the transfer switch and the main distribution above the expected flood level, either on a raised platform or in an upper level plant room. Our article on flood resilience for emergency generators covers the details.

In storm regions, the enclosure and its fixings must withstand design wind speeds, and the air intakes and exhaust must be protected from wind-driven rain and debris. Keep the exhaust away from doors, windows and air intakes, because a shelter full of people is especially vulnerable to fumes entering the building.

Fuel runtime when roads are closed

After a major storm, fuel deliveries may be impossible for days. Size the on-site fuel store for the shelter’s expected duration at its expected load, with a margin, and agree a priority delivery arrangement with more than one supplier. A plan for fuel resupply during a regional emergency should be part of the shelter plan, not an afterthought.

Stored diesel in a tank that is rarely used must be kept in good condition. Regular sampling, water removal and filtration prevent the fuel from blocking filters during the first long run. Some shelters add solar panels and batteries for lighting and charging, which stretches the fuel further; our page on hybrid power systems explains how such systems are combined.

Transfer, manual operation and noise

An automatic transfer switch is preferable, because shelter staff may be volunteers with no electrical training. Even so, the building should have clear written instructions for manual start and transfer, posted next to the switch, in case automatic operation fails.

A shelter is where people sleep. Locate the generator away from the main hall, select an enclosure with suitable acoustic performance and avoid placing the exhaust outlet near windows of sleeping areas. Noise that is acceptable for a short test can be exhausting when it runs all night for a week.

Keeping a dual-use building ready

Most of the year the building is a school or sports venue, and the generator can easily be forgotten. A regular exercise schedule, under load where possible, keeps it ready. Our guide to exercise testing for emergency diesel generators sets out a suitable routine.

Before each storm season, run a full test with the shelter panel loaded, check fuel level and condition, confirm the transfer switch operates and walk through the instructions with the people who will run the shelter. The facilities team and the emergency management agency should both hold a copy of the test record.

About the authors

This guide comes from the USP&E standby and emergency power engineering team. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. How we keep standby sets ready year round is outlined on our operations and maintenance page.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Shelter generator questions

What size generator does an emergency shelter need?

It depends on the essential loads and occupancy. As an illustration, a sports hall for about 300 people might need around 160 kW running load and a set near 250 kVA.

Which loads should a shelter generator carry?

Lighting, fire alarm, heating or cooling for the main hall, kitchen and refrigeration, medical device outlets, charging, communications and water pumps.

Should the generator power the whole building?

Not necessarily. A dedicated shelter panel carrying only essential circuits allows a smaller set and longer runtime from the same fuel.

How much fuel should a shelter store?

Enough for the expected shelter duration at expected load plus margin, since deliveries may be impossible for days after a major storm.

Where should a shelter generator be installed?

Above the expected flood level, in a wind-rated enclosure, with the exhaust kept away from doors, windows and sleeping areas.

How often should a shelter generator be tested?

Exercise it on a regular schedule, under load where possible, and run a full test with the shelter loads before each storm season.

Plan a shelter generator

Send the building plans, expected occupancy and the essential load list, and our engineers will propose a generator, panel and fuel arrangement.

Phone +27 10 822 2324 during office hours, or write to info@uspeglobal.com at any time; the emergency power enquiry page also routes straight to our project engineers. Standby rated sets are listed in our diesel generator inventory.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · Emergency Diesel Generators is part of USP&E