This guide explains how emergency generators are sized and arranged for treatment plants.
Which loads are critical
At a drinking water plant, the critical loads are usually raw water intake pumps, treatment process equipment, chemical dosing, high-lift pumps and controls. At a wastewater plant, inlet pumping, screening, aeration blowers and the controls come first. Many plants also back up laboratory, lighting and security systems.
List these loads with their ratings and starting methods. Not every pump must run at once; the operators can say what the minimum safe operation looks like.
Pump and blower starting decides the size
Large induction motors draw several times their full-load current when started direct-on-line. A generator that easily carries the running load may still collapse in voltage when a big pump starts. Variable speed drives and soft starters reduce the starting demand, but drives also create harmonics that the generator must tolerate.
A proper sizing study models the starting sequence, the voltage dip on each step and the harmonic content. Our generator sizing chart gives the basic kW, kVA and amps relationships.
Runtime and fuel
Outages at water plants can last days after storms or floods, and fuel deliveries may be difficult in exactly those conditions. Many utilities choose longer on-site fuel storage than a commercial building would, plus a priority resupply agreement.
Flood risk should also shape where the generators and tanks sit; raising them above the flood level is common practice.
Transfer scheme and controls
Larger plants often have several incoming feeders and several generators connected to a main switchboard. The transfer scheme must restart the critical pumps in the right order after power returns, so that the generators are not overloaded by everything starting at once.
Integration with the plant SCADA lets operators see generator status, fuel level and alarms alongside the process.
Small pumping stations and lift stations
Water networks also include many small pumping and lift stations spread across a town. Each one may only need a modest generator, but an overflow at any of them can cause environmental damage. Options include permanent sets at the most critical stations and a plan to bring towable sets to the others.
Standardising the connection points, cable sizes and phase rotation at every station makes it much faster to connect a towable set during an outage. Clear labelling and a printed connection procedure at each station help crews who may be working at night in bad weather.
Testing and readiness
Weekly or monthly exercising, annual load tests and a full test with the plant on generator power confirm readiness. A test that actually transfers the process loads is the only way to prove the motor starting sequence works. Our page on emergency generator installation covers the commissioning steps.
About USP&E
USP&E designs, installs and maintains emergency and prime power plants as an EPC and O&M contractor, not a broker. We have 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years of experience. Our engineering and EPC services include sizing studies and transfer schemes.
Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.
Questions about generators for water plants
What size generator does a water treatment plant need?
Enough to run the minimum safe process load and to start the largest pumps in sequence without excessive voltage dip. A starting study confirms it.
Do variable speed drives help generator sizing?
They reduce starting current, but they add harmonics, so the generator and its voltage regulator must be chosen to handle them.
How long should a water plant generator be able to run?
Many utilities plan for longer runtimes than commercial buildings, because outages after storms or floods can last days.
Where should generators be placed at a treatment plant?
Above the expected flood level, with safe fuel delivery access and short cable runs to the main switchboard.
Protecting a water or wastewater plant?
Send us the motor list, single-line diagram and outage history, and we will propose a generator size, fuel plan and transfer sequence.
Phone +27 10 822 2324, email info@uspeglobal.com with your site data, or go through the utilities enquiry form. Emergency sets in stock are in the diesel generator inventory.